Construction Status (April, 2018) – The Address, Gulshan, Dhaka

Construction Status

Serial No. Name of work Achievement up to March 2018 Program  Up to  April 2018
Target Achievement Target
01 Wall Tiles at all floor

 

100%

 

100%

 

02 Sliding ver grill fitting at all floor

 

100%

 

100%

 

03 Ver. Railing work

 

100%

 

100%

 

04 Swimming pool Tiles work

 

100%

 

100%

 

05 Paint work (Rubbing)

 

100%

 

100%

 

06 G.F all Civil work construction

 

100%

 

100%

 

07 Roof top GI wiring work

 

100%

 

100%

 

08 Marble Polish work

 

50%

 

50%

 

60%
09 Fire Hydrent work at all floor

 

80%

 

80%

 

85%
10 Paint work (1st coat)

 

40%

 

40% 60%
11 Thai Alluminium Work

 

30%

 

30% 40%
12 Bathroom Wall Pointing

 

20%

 

20% 50%


Some of the project picture