Construction Status (January, 2018) – The Address, Gulshan, Dhaka

Achievement Program for the month of December, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 13th floor Swimming pool construction work 75% 75% 25%
2 Electric groove cutting & coduite work at all floor 85% 85% 5%
3 Door Frame fitting work all floor 85% 85% 5%
4 Inside plaster work (completed up to 11th floor) at 12th floor. 30% 30% 10%
5 Inside plaster work 13th floor. 15% 15% 10%
6 Outside plaster 45% 40% 15%
7 Window Grill fitting at all floor 10% 10% 10%
8 Sanitary internal wiring at all floor 70% 70% 10%
9 Wall Tiles at all floor 60% 60% 10%
10 Floor marble fitting work at all floor 30% 30% 20%
11 Pavement tiles work at basement 50% 40% 25%
12 Column guard tiles at Basement floor 50% 50% 10%

Program for the month of January, 2017

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 13th floor Swimming pool construction work 100% 25%
2 Electric groove cutting & coduite work at all floor 90% 5%
3 Door Frame fitting work all floor 90% 5%
4 Inside plaster work (completed up to 11th floor) at 12th floor. 40% 10%
5 Inside plaster work 13th floor. 25% 10%
6 Outside plaster 55% 15%
7 Window Grill fitting at all floor 20% 10%
8 Sanitary internal wiring at all floor 80% 10%
9 Wall Tiles at all floor 70% 10%
10 Floor marble/Tiles fitting work at all floor 40% 10%
11 Pavement tiles work at basement 50% 10%
12 Column guard tiles at Basement floor 50% 0%

Some of the project picture