Construction Status (February, 2018) – The Crescent, Bashundhara, Dhaka

Achievement Program for the month of January, 2018

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRESS UP TO THIS MONTH PROGRESS IN THIS MONTH
1 General floor tiles 100% 100% 5%
2 Facing bricks 100% 100% 5%
3 GF civil works 100% 100% 10%
4 Parking Tiles 100% 30% 30%
5 Internal paints, 1st coat 100% 100% 50%
6 External paints 100% 100% 60%
7 Boundary grill 50% 50% 50%

Program for the month of February, 2018

SL. NO. DESCRIPTION OF WORK PROGRAMME UP TO THIS MONTH PROGRAMME IN THIS MONTH
1 Internal paint, 2nd coat 100% 100%
2 External paint 100% 100%
3 Parking tiles 100% 70%
2 Electrical switch sockets 100% 100%
3 Sanitary fixtures 100% 100%
4 Aluminium works 100% 100%
5 GF wooden ceiling 100% 100%
6 BTI logo 100% 100%
7 Fire alarm, CCTV etc 100% 100%