Construction Status (February, 2018) – The Prestige, Hill View HS, Chittagong

Achievement for the month of January -2017

Sl No. Description of Works Program for the month of

Januaray-2018

Achievement for the month of January-2018 Overall achievement up to this month
1 Aluminum fitting work B1+C1+ A2+B2+C2+A3+B3+C3+A4+B4+C4+A5+B5+C5 20% 20% 100%
2 Boundary wall (RCC & Plaster) 50% 50% 100%
3 Aluminum work  (6th to 9th floor) 30% 30% 100%
4 Ground floor Sanitary RCC Pipe line work 50% 50% 100%
5 Paint work (1st coat), 1st to 5th floor 50% 50% 100%
6 Paint work (Sealer & putty) 6th to 9th floor 50% 50% 100%
7 Electrical cable wiring (ground floor) 30% 30% 100%
8 Sub-main cable wiring 50% 50% 100%
9 TV, Telephone, Int. Vertical cable line 50% 50% 100%
10 Main door Shutter fitting all floor 100% 100% 100%
11 Internal door shutter fitting 50% 50% 50%
12 Pavemant tiles fitting (basement) 80% 80% 80%
13 Main gate fitting, Parking grill & Sub-station door fitting 100% 100% 100%
14 Outside sealer & putty work 80% 80% 80%
15 Outside paint work (1st coat) 50% 50% 50%
16 Rooftop patenstone work 100% 100% 100%
17 All Void plaster with NCF & patenstone work 100% 100% 100%

                                                           Program for the month of  February 2018

Sl No. Description of Works Program for the month of

February-2018

Predicted future achievement up to February-2018
01 Boundary wall (Brick work & Plaster) West & North Side 100% 100%
2 Paint work (1st coat), 6th  to 9th floor 100% 100%
3 Paint work (2nd coat), 1st  to 9th floor 80% 80%
4 Paint work (Sealer & putty) common area 70% 70%
5 Paint work (1st coat) common area 50% 50%
6 Internal door shutter fitting 50% 100%
7 Pavemant tiles fitting (basement) 20% 100%
8 Pavemant tiles fitting (ground floor) 50% 50%
9 Outside sealer & putty work 20% 100%
10 Outside paint work (1st coat) 50% 100%
11 Ground Floor Wooden False Ceiling 70% 70%
12 Boundary Wall Grill fitting 100% 100%
13 Logo & Boundary Wall Ceramics 50% 50%
14 Community Tiles Works 100% 100%
15 Switch, Scoket fittings 50% 50%
16 Pointing works (Bath & Kitchen Room) 50% 50%