January 2021, Celestial Heights, Gulshan-1, Dhaka
| |
---|
Name of the work | Progress details |
Foundation work | 100% completed |
Sub-Structure | Mat casting Works 100% completed, Retaining Wall including UGWR &Ramp casting Works 100% completed, 1st Basement Roof Works 100% completed. |
Super Structure work | G.F. Roof casting work 100% completed. 1st Floor Roof slab casting work 100% completed. 2nd Floor Roof slab casting work 100% completed. 3rd Floor Roof slab casting work 100% completed. 4th Floor Roof slab casting work 100% completed. 5th Floor Roof slab casting work 100% completed. 6th Floor Roof slab casting work 100% completed. |
Block Work | N/A |
Electrical conduting work | Basement floor 80% done, 1st floor 30% done, |
Door frame fitting work | N/A |
Sanitary & plumbing line work | N/A |
In side Plastering work | Basement Ceiling plaster 60% Completed . 1st Floor Ceiling plaster 60% Completed . 2nd Floor Ceiling plaster 40% Completed . |
Electrical cable wiring work | N/A |
Wall tiles work | N/A |
Common sanitary & Plumbing line work | N/A |
Outside plastering work | N/A |
Floor tiles/Marble work | N/A |
L.C.C work | N/A |
Grill & Railing work | N/A |
Inside paint & Polishing work | N/A |
Switch -Socket fitting work | N/A |
Outside paint work | N/A |
Door shutter work | N/A |
Aluminum/Glazing work | N/A |
Tiles Pointing work & Marble finishing work | N/A |
Commode - Basin fitting work and C.P fittings work | N/A |
Lift/Generator /Substation /Solar work | N/A |
Boundary wall /Ground floor development work | N/A |
Roof top finishing work | N/A |
Roof top Gardening work | N/A |