March 2021 – The Muse at Khilgaon, Dhaka
| |
---|
Name of the work | Progress details |
Foundation work | Completed. |
Super Structure work | 6rd floor roof completed.7th floor roof on going. |
Block Work | 2nd floor 70%,3rd floor 70% ,4th floor-50%,5th floor-10%Completed. |
Electrical conduting work | |
Door frame fitting work | |
Sanitary & plumbing line work | |
In side Plastering work | |
Electrical cable wiring work | |
Wall tiles work | |
Common sanitary & Plumbing line work | |
Outside plastering work | |
Floor tiles/Marble work | |
L.C.C work | |
Grill & Railing work | |
Inside paint & Polishing work | |
Switch -Socket fitting work | |
Outside paint work | |
Door shutter work | |
Aluminum/Glazing work | |
Tiles Pointing work & Marble finishing work | |
Commode - Basin fitting work and C.P fittings work | |
Lift/Generator /Substation /Solar work | |
Boundary wall /Ground floor development work | |
Roof top finishing work | |
Roof top Gardening work | |
No comments yet