March 2021 – Junction 54 at Uttara
| |
---|
Name of the work | Progress details |
Foundation work | 100% complete. |
Super Structure work | 99 % complete. |
Block Work | 1st to 9th floor block work 99% complete. |
Electrical conduting work | 2nd to 9th floor roof slab conduiting work 100% complete. 2nd floor to 9th floor wall conduting & Mk box fitting 95% complete. |
Door frame fitting work | 2nd floor to 9th floor door frame fitting work 98% complete. |
Sanitary & plumbing line work | Sanitary & plumbing works 70% |
In side Plastering work | 1st floor to 8th floor plastering work 97% complete. |
Electrical cable wiring work | 2ND -9TH floor cable wiring work 90% complete. |
Wall tiles work | 30% WALL TILES COMPLETE |
Common sanitary & Plumbing line work | N/A |
Outside plastering work | ON GOING |
Floor tiles/Marble work | N/A |
L.C.C work | N/A |
Grill & Railing work | N/A |
Inside paint & Polishing work | N/A |
Switch -Socket fitting work | N/A |
Outside paint work | N/A |
Door shutter work | N/A |
Aluminum/Glazing work | N/A |
Tiles Pointing work & Marble finishing work | N/A |
Commode - Basin fitting work and C.P fittings work | N/A |
Lift/Generator /Substation /Solar work | N/A |
Boundary wall /Ground floor development work | N/A |
Roof top finishing work | N/A |
Roof top Gardening work | N/A |
| |