March 2021 – Green Meadow at Bashundhara R/A
| |
---|
Name of the work | Progress details |
Foundation work | Foundation work 100% completed . |
Super Structure work | 5 th Floor ceiling plaster 100% completed.7th floor roof slab shutter on Going , |
Block Work | 1 st Floor Block work 100% Complete and 2 nd Floor Block 100% 3 rd floor 95 % Complete 4th floor 85% Complete. 5th floor 45% Complete. |
Electrical conduting work | 1 st Floor Wall Conduit 100% Complete.2 nd Floor 100% ,3rd Floor 100% Complete.4 th floor 85 % Complete. 5 th floor 45 % Complete. |
Door frame fitting work | 1 st Floor 100% Complete,2 nd Floor 100% complete. 2 Rd Floor 80% complete. |
Sanitary & plumbing line work | N/A |
In side Plastering work | G.F Plaster 60% Complete.1 st Floor 98 % complete.2 nd floor 90 % Complete. 3Rd floor 80 % Complete. |
Electrical cable wiring work | 1 st Floor 30% Complete |
Wall tiles work | N/A |
Common sanitary & Plumbing line work | N/A |
Outside plastering work | N/A |
Floor tiles/Marble work | N/A |
L.C.C work | N/A |
Grill & Railing work | N/A |
Inside paint & Polishing work | N/A |
Switch -Socket fitting work | N/A |
Outside paint work | N/A |
Door shutter work | N/A |
Aluminum/Glazing work | N/A |
Tiles Pointing work & Marble finishing work | N/A |
Commode - Basin fitting work and C.P fittings work | N/A |
Lift/Generator /Substation /Solar work | N/A |
Boundary wall /Ground floor development work | N/A |
Roof top finishing work | N/A |
Roof top Gardening work | N/A |