February 2021, Green Valley, Chattogram
| |
---|
Name of the work | Progress details |
Foundation work | Tower-1 Foundation work 100% completed. Tower-2 Foundation 30% completed. |
Super Structure work | Tower-1: 12% Completed |
Brick / Block Work | N/A |
Electrical conduting work | N/A |
Door frame fitting work | N/A |
Sanitary & plumbing line work | N/A |
In side Plastering work | N/A |
Electrical cable wiring work | N/A |
Wall tiles work | N/A |
Common sanitary & Plumbing line work | N/A |
Outside plastering work | N/A |
Floor tiles/Marble work | N/A |
L.C.C work | N/A |
Grill & Railing work | N/A |
Inside paint & Polishing work | N/A |
Switch -Socket fitting work | N/A |
Outside paint work | N/A |
Door shutter work | N/A |
Aluminum/Glazing work | N/A |
Tiles Pointing work & Marble finishing work | N/A |
Commode - Basin fitting work and C.P fittings work | N/A |
Lift/Generator /Substation /Solar work | N/A |
Boundary wall /Ground floor development work | N/A |
Roof top finishing work | N/A |
Roof top Gardening work | N/A |