March 2021, Afnaan, Lalmatia,Dhaka
| |
---|
Name of the work | Progress details |
Foundation work | Completed. |
Super Structure work | Completed. |
Block Work | Completed. |
Electrical conduting work | Completed. |
Door frame fitting work | Completed. |
Sanitary & plumbing line work | 1st to 8th floor 80%Completed. |
In side Plastering work | Completed. |
Electrical cable wiring work | 1st floor—8TH floor completed. |
Wall tiles work | 1st floor wall tiles-60%,3rd -5th floor wall tiles -60%completed. |
Common sanitary & Plumbing line work | 50% Completed. |
Outside plastering work | 90%East side,30% west side,90%south side, North side 10% completed |
Floor tiles/Marble work | |
L.C.C work | |
Grill & Railing work | |
Inside paint & Polishing work | |
Switch -Socket fitting work | |
Outside paint work | |
Door shutter work | |
Aluminum/Glazing work | |
Tiles Pointing work & Marble finishing work | |
Commode - Basin fitting work and C.P fittings work | |
Lift/Generator /Substation /Solar work | Substation room—85%completed.Solar –completed.Lift room—80%completed. |
Boundary wall /Ground floor development work | Boundary wall—5% completed. |
Roof top finishing work | |
Roof top Gardening work | |