March 2021- Spring Dale, Khilkhet, Dhaka
| |
---|
Name of the work | Progress details |
Foundation work | Foundation work-100%. |
Super Structure work | Roof top works-70%. |
Block Work | Block works at 1st-6th floors-100%, 7th-8th floors-80% complete. |
Electrical conduit work | As above. |
Door frame fitting work | 1st-5th floors-100% complete. |
Sanitary & plumbing line work | 1st-2nd floor- 100% complete. |
In side Plastering work | 1st-3rd floor-100% complete. |
Electrical cable wiring work | As above. |
Wall tiles work | Under progress. |
Common sanitary & Plumbing line work | N/A |
Outside plastering work | N/A |
Floor tiles/Marble work | N/A |
L.C.C work | N/A |
Grill & Railing work | N/A |
Inside paint & Polishing work | N/A |
Switch -Socket fitting work | N/A |
Outside paint work | N/A |
Door shutter work | N/A |
Aluminum/Glazing work | N/A |
Tiles Pointing work & Marble finishing work | N/A |
Commode - Basin fitting work and C.P fittings work | N/A |
Lift/Generator /Substation /Solar work | N/A |
Boundary wall /Ground floor development work | N/A |
Roof top finishing work | N/A |
Roof top Gardening work | N/A |