March 2021 – Ambiance, Moghbazar, Dhaka
| |
---|
Name of the work | Progress details |
Foundation work | Completed. |
Super Structure work | Completed. |
Block Work | 90%-Completed. |
Electrical conduting work | Completed. |
Door frame fitting work | 1ST floor -8th floor-Completed. |
Sanitary & plumbing line work | 2nd floor to 7th floor Completed. |
In side Plastering work | 1st floor to 7th floor completed. |
Electrical cable wiring work | 4th floor completed. |
Wall tiles work | 4th floor 7th floor-85% completed, |
Common sanitary & Plumbing line work | 70%Completed. |
Outside plastering work | North side 60%Completed.East Side 90% Completed, West Side-90% Completed. |
Floor tiles/Marble work | |
L.C.C work | |
Grill & Railing work | |
Inside paint & Polishing work | |
Switch -Socket fitting work | |
Outside paint work | |
Door shutter work | |
Aluminum/Glazing work | |
Tiles Pointing work & Marble finishing work | |
Commode - Basin fitting work and C.P fittings work | |
Lift/Generator /Substation /Solar work | Substation-45% |
Boundary wall /Ground floor development work | |
Roof top finishing work | |
Roof top Gardening work | |