March 2021 – The Destination, Dhanmondi, Dhaka.
| |
---|
Name of the work | Progress details |
Foundation work | Phase-1 foundation work 100% ,retaining wall 100%, UGWR 100%, ramp casting 100%, basement column casting 100%, basement roof slab casting 100%, Phase- 2 . Earth cutting 100%, footing casting 100%, mat casting 40% |
Super Structure work | Phase – 1 G.Floor column casting 100%, G.Floor roof casting 100% ,1st floor column casting 80%, |
Block Work | |
Electrical conducting work | |
Door frame fitting work | |
Sanitary & plumbing line work(Ace drain water line, ven- vertical line) | |
In side Plastering work | |
Electrical cable wiring work | |
Wall tiles work | |
Common sanitary & Plumbing line work | |
Outside plastering work | |
Floor tiles/Marble work | |
L.C.C work | |
Grill & Railing work | |
Inside paint & Polishing work | |
Switch -Socket fitting work | |
Outside paint work | |
Door shutter work | |
Aluminum/Glazing work | |
Tiles Pointing work & Marble finishing work | |
Commode - Basin fitting work and C.P fittings work | |
Lift/Generator /Substation /Solar work | |
Boundary wall /Ground floor development work | |
Roof top finishing work | |
Roof top Gardening work | |
| |